1. What is project management? Discuss the components of project feasibility analysis with suitable examples.
2. Discuss the importance of market and demand analysis in project management.
3. Draw a network diagram for the activities given below and determine the critical path.
Activity Description Predecessor Duration (Months)
A Design Plant – 12
B Select Site A 8
C Select Vendor A 4
D Select Personnel A 3
E Prepare Site B 12
F Manufacture Generator C 18
G Prepare Operations Manual C 5
H Install Generator E,F 4
I Train Operators D,G 9
J Obtain License H,I 6
4. What is Work Breakdown Structure (WBS)? Develop a WBS for a project in which you are going to build a bicycle. Try to identify all the major components and provide three levels of detail.
5. Discuss the role of Total Quality Management practices in Project Management.